Package Mainly consisting of a new concrete warehouse ground floor slab with 5m high push walls. Other elements include weigh bridges, hard-standing and other isolated concrete base structures. – Situated in Hull city centre, the construction of a new waste recycling facility.
Main slab areas has had to be split into four pours containing roughly 400m3 per pour. During a tight programme the construction of the walls followed directly on from the formation of the slabs.
At 5m in height and pours of around 45m in length the completion of the walls was hit ahead of target of around 5 weeks. Great going by the site team.