On this project we have been responsible for construction of FRC Distribution Kiosk, transformer bunds, Chemical tank Bund and other FRC structures around the site. We have poured over 380 m3 of concrete and installed over 65 t of Reinforcement

  • Our works Included:
  • Installation of Heave protection
  • Installation of Root Protection
  • Fixing Reinforcement
  • Installation of formwork
  • Pouring concrete to bases and walls

    Works Value exceeded £ 200 k on LO basis
Contract Value
£200k
Principal Contractor
FRC Distribution Kios